Linear Project-Scheduling Optimization Considering a Reverse Construction Scenario

Ze Yu, Chuxin Wang, Yuanyuan Zhao, Zhiyuan Hu, Yuanjie Tang

APPLIED SCIENCES-BASEL(2023)

引用 0|浏览1
暂无评分
摘要
The linear scheduling method (LSM) for optimization in linear projects has been the focus of numerous academic studies over the years. However, research on incorporating reverse construction activities and other practical scenarios, such as flexible activity-section-crew assignment demands, in linear project-scheduling optimization remains insufficient. This has further spurred research on practical scenario-based linear project-scheduling optimization. We performed an analysis of a description method system within the LSM framework, outlining the spatiotemporal logical relationship in scenarios involving reverse activities. A scheduling optimization model incorporating a flexible constraint system, capable of handling multisection-multicrew, multicrew-multimode, and multicrew-multiconstruction direction scenarios is developed to enhance the practicability of linear project-scheduling optimization. Additionally, an advanced grey wolf optimization (GWO) algorithm is devised and validated through a real-world case study. The case study provides insights into the impact of reverse construction activities on the linear project-scheduling problem, specifically in the dimension of project duration.
更多
查看译文
关键词
railway infrastructure,linear scheduling method,scheduling optimization,construction project management,grey wolf optimizer
AI 理解论文
溯源树
样例
生成溯源树,研究论文发展脉络
Chat Paper
正在生成论文摘要