雷神山医院标准隔离病区样板施工技术
Installation(2020)
Abstract
针对雷神山医院隔离病区室内机电工程仅有10天工期的要求,项目在隔离病区机电专业施工过程中以样板先行,进行标准模块拆分,极短时间内在样板区间集中解决病区施工技术问题,并优化出切实可行便捷的施工方案,为后续全面铺开作业与穿插施工确定了方向.