Chrome Extension
WeChat Mini Program
Use on ChatGLM

猴子岩水电站面板堆石坝堆石体变形控制措施

wf(2018)

Cited 0|Views2
No score
Abstract
猴子岩水电站面板堆石坝最大坝高223.5 m,坝址区河谷狭窄,河床覆盖层深厚,地震烈度高,要求采取有效措施,控制大坝堆石体在面板施工后期的变形量.详细介绍了在工程设计、施工过程中针对堆石体变形提出的控制思路、采取的措施,以及实际的实施效果,可为深窄河谷高面板堆石坝的设计与施工提供参考.
More
AI Read Science
Must-Reading Tree
Example
Generate MRT to find the research sequence of this paper
Chat Paper
Summary is being generated by the instructions you defined