A distributionally robust analysis of the program evaluation and review technique

European Journal of Operational Research(2021)

引用 7|浏览17
暂无评分
摘要
•We consider project planning from a distributionally robust perspective.•We formulate tight lower and upper bounds for the expected project duration.•The approach is used to analyze the perceived downsides of the standard techniques.•The gap between the best- and worst-case expected project duration is at most 3%.