1036MW机组的电气整套启动调试

Electric Power Construction(2010)

Cited 6|Views6
No score
Abstract
介绍了华能海门电厂1号1036 MW机组的设备特点以及首次电气整套启动试验的过程,并阐述了启动过程中暴露出的问题及相应的分析处理;针对厂用电切换存在的弊端,提出了改造设想,以期为今后大型机组的启动调试提供借鉴.
More
Translated text
Key words
auxiliary power supply,million-kilowatt unit,distributed control system,start-up and debugging,generator,electrical renovation